TASK 6 SURFACE DRAINAGES: ROLLING DIPS <br /> Rolling dips may be constructed on some roads. The purpose of these dips is to facilitate the <br /> removal of water from the roads to the outslope before the water is concentrated by long flow <br /> paths. The locations of these dips will be marked in the field by the PROJECT MANAGER. <br /> The rolling dips will be built to the following specifications and as shown on Figure 1 , unless <br /> otherwise directed by the PROJECT MANAGER: <br /> From the lowest point of the dip, excavation will proceed down the road for a distance of <br /> twenty (20) feet, and up the road for a distance of approximately eighty (80) feet. The dip <br /> shall be uniformly sloped toward the low point of the dip from each end of the dip. The low <br /> point of the dip will generally be about two (2) feet below the elevation of the down gradient <br /> lip of the rolling dip. There will be some variation in dimensions due to variations in road <br /> grade. Five (5) cubic yards of riprap with an average diameter of eight (8) inches will be <br /> dumped on the road outslope below the rolling dip outlet. An additional twenty two (22) <br /> cubic yards of rip rap material with an average diameter of six (6) inches will be uniformly <br /> placed at the bottom of each rolling dip parallel with the dip drainage pattern. <br /> Rolling dips will be constructed on each of the following roads. The estimated number of <br /> rolling dips and the estimated aggregate width of the rolling dips is tabulated below: <br /> Location Number of Dios Width <br /> Mine 1 Fan Road 4 140 <br /> Mine 2 Fan Road 1 35 <br /> Mine 2 Road 1 40 <br /> Coal Silo Road 1 55 <br /> Measurement and Payment <br /> The rolling dips will be paid for per rolling dip installed for the unit price shown under Item 6 <br /> of the Bid Schedule. Payment for this task will be at prices established in Item 6 of the <br /> Invitation and Bid Sheet per Rolling Dip installed. Such Payment shall be considered full <br /> compensation for all labor, materials, equipment and all other items necessary and incidental <br /> to the furnishing and placement of the Rolling Dips as directed and described in the <br /> specifications. Payment will be as this task is completed and approved by the PROJECT <br /> MANAGER. Payment for this task will be made only for the unit prices shown under Item 6 <br /> of the Bid Schedule. <br /> 22 <br />