Laserfiche WebLink
** ADJUSTED DOZER TIME AND HOURLY RATE <br /> Bid dozer FHP = 410 @ $114/hr. Used = 330FHP. 330 divided by 410 times $114 = <br /> $91.76/hr. Figuring hours: Item 2. bid $7,980.00 divided by $91.76/hr. _ <br /> 86.9hrs. Item 4. bid $4,560.00 divided by $91.76 = 49.7hrs. Total additional <br /> dozer time for the project equals 136.6 hours. <br /> ** ADJUSTED EXCAVATOR TIME AND HOURLY RATE <br /> Bid excavator FHP = 58 @ $57/hr. Used 180FHP. 180 divided by 58 times $57 = <br /> $176.90/hr. (for a 1979 Drott excavator! ) Figuring hours: Item 7. bid $2,280 <br /> divided by $176.90 = 12.9 hours <br /> TOTAL EXCAVATOR HOURS USED <br /> Excavator hours totaled 34.5 minus 12.9 (Item 7 hours) = 21.7 hrs. TO CONVERT TO <br /> DOZER TIME. 21.7hr. times $176.90 (revised FHP rate) _ $3,838.73 divided by <br /> $91.76 (revised dozer rate) = 41.8 hrs <br /> TOTAL DOZER HOURS USED <br /> Dozer hours totaled 109.5 less 10hrs. (per 9/4 narr. below) = 99.5 plus 41.8hrs. <br /> = 141.3 hrs. <br /> DATE PRECIPITATION <br /> 9/4 Encounter excavator being demobilized. Directed DR/WSR that <br /> unauthorized hours will not be paid by MLRD. Operator blatantly <br /> tried to finish by removing dozer accessways and by final grading <br /> to his "plan". Negotiated that from a total of 20hrs of dozer <br /> time, 10 hours will not be accepted. All of the 9hrs. of <br /> excavator time would be accepted. Operator had same complaints <br /> regarding the power poles being in the way. Finally receive FHP <br /> for each machine. Dozer = 330, exc. = 180. <br />