COAL BASIN PROJECT <br /> Extra Machine hour recap <br /> (From submitted Vaughn-Michael Construction Time sheets) <br /> DATE MACHINE HOURS WORK DESCRIPTION <br /> 8/13 Dozer 2 Level strip bench area <br /> 8/19 Dozer 7 Level strip bench area <br /> Dozer 2 Rework Channel A runout area <br /> 8/21 Dozer 10 Finish strip bench area <br /> 8/22 Dozer 1 Rework Channel A runout area <br /> Dozer 3 Dozed holding ponds for strip area runoff <br /> 8/23 Dozer 5 Topsoil stockpiling - lower coal waste <br /> Excavator 4 Worked top of coal waste pile slope <br /> 8/26 Dozer 10 Coal pile relocation <br /> Excavator 7 Pulled coal waste <br /> 8/27 Dozer 9 Leveling lower coal waste pile <br /> Excavator 8* Pulled coal waste <br /> 8/28 Dozer 4.5 Leveled coal waste pile <br /> Excavator 3.5 Worked bottom of coal waste pile slope <br /> 8/29* Dozer 8 Coal waste pile "Lanscape" <br /> Excavator 3 Sloping pile <br /> 8/30* Dozer 9 Coal waste pile "Landscaping" <br /> Excavator 6 "Work back along slope" <br /> 9/3* Dozer 7 "Landscape waste coal piles" <br /> Excavator 3 Pulled back slope along creek <br /> 9/8* Dozer 9 Working slope back along lower waste pile <br /> 9/9 Dozer 6.5 Worked coal waste pile <br /> 9/10 Dozer 9 Coal waste pile slopes, "riprap" slope <br /> bottom, cut ditch to south <br /> 9/11 Dozer 1 Ditch work adj. to coal waste pile <br /> 9/13 Dozer 2.5 Finaled top access & ponds out strip area <br /> 9/14 Dozer 4 Road reclaim on top, Ditch work on bottom <br /> Grand Total Dozer 109.5 <br /> Grand Total Excavator 34.5 <br /> * Discrepancy 8/27 time submitted to me shows 8 hrs. , submitted to WSR shows 9 <br /> Do not have "Vaughn-Michael" time sheets for 8/29 - 9/8. Only have sheets to <br /> Cat Constr. <br />