My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
1997-07-25_HYDROLOGY - M1977378
>
Day Forward
>
Hydrology
>
Minerals
>
M1977378
>
1997-07-25_HYDROLOGY - M1977378
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
2/28/2021 8:25:02 AM
Creation date
7/18/2012 7:33:26 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1977378
IBM Index Class Name
HYDROLOGY
Doc Date
7/25/1997
Doc Name
June, 1997 Monthly/ 2nd Quarter Report
From
Sunnyside Gold Corp
To
CDPHE-WQCD
Permit Index Doc Type
Hydrology Report
Media Type
D
Archive
No
Tags
DRMS Re-OCR
Description:
Signifies Re-OCR Process Performed
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
14
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
June 1997 Monthly Report <br /> Page 2 <br /> Capping material was hauled to the site where needed. <br /> During June, the site was seeded with Sunnyside's MLR seed mix <br /> (Mountain Mix) specified for sites the same elevation as the <br /> Boulder Creek Tailings site. After seeding, the site was <br /> mulched with grass hay spread by an aeromulcher. <br /> Planned future activity consists of monitoring and maintenance <br /> with possible additional planting of shrubs and trees. <br /> A completion certification and inspection request was <br /> submitted for this site in June. DMG inspected the site and <br /> concurs that reclamation was in accordance with MLR standards. <br /> Progress pictures taken in June, 1997 are included with this <br /> report. <br /> - Columbus Mine Portals - Mine Waste Dumps <br /> This is a "B List" project. Therefore, no work, permitting or <br /> arrangement for access is planned until it becomes evident <br /> that the work plan for this project requires implementation. <br /> - Surface Mill Tailings at Eureka <br /> During June and the 2nd quarter, scrap and trash were removed <br /> from the site. Additional work including site neutralization, <br /> minor grading, erosion protection for a portion of the Eureka <br /> Creek bank and site planting is planned for July after high <br /> water conditions recede. <br /> Site progress pictures taken in June 1997 are included with <br /> this report. <br /> - Gold Prince - Mill Tailings <br /> No work was done on this project in June or the 2nd quarter <br /> due to snow-cover. Access to the site was possible in June <br /> but the entire site was snow-covered. Mobilization for <br /> installation of the portal bulkhead is planned for late July. <br /> Progress pictures for this site are not included in this <br /> report due to snow-cover. <br /> - Ransom Tunnel <br /> The bulkhead was poured on June 191 1997 after a pre-pour <br /> inspection by DMG on June 16, 1997 . 7-day compressive <br /> strengths of test cylinders averaged 4737 psi which is the <br /> average of 4 compressive strength tests. The lowest result <br /> was 3470 psi. All results were over the 3000 psi design <br /> strengths. Bulkhead concrete-rock contact grouting was <br /> started by month-end. <br />