TASK 1 MOBILIZATION AND DEMOBILIZATION <br />This task shall comply with specification 1.0, Mobilization/Demobilization, attached. <br />Measurement and Payment <br />There will be no measurement for payment. Payment for this task will be reflected in a lump sum <br />bid under Item 1 on the Bid Schedule. This lump sum bid will cover all costs for Mobilization and <br />Demobilization. Payment shall be made as described in specification 1.0, <br />Mobilization/Demobilization, attached. <br />TASK 2 EARTH WORK <br />CONTRACTOR, in conjunction with PROJECT MANAGER will stake the boundaries of <br />the area of the Old Refuse Pile to be affected by this project. This will occur prior to initiating <br />any work within the Project area. <br />The earth work portion of this project consists of reducing the north slope of the Old Refuse <br />Pile to the design specification of 2H:1V. Material excavated from the Pile will be transported <br />to the designated disposal site. Map 4, Old Refuse Pile, depicts the current topography of the <br />facility, locations of Cross Sections A through H and outlines the portion of the facility which <br />is subject to this Project. Map 3, Project Area, depicts the location where the excavated <br />materials will be placed, and the location of the topsoil stock pile from which the topsoil will <br />be derived. Map 5, Reclaimed Topography, depicts the post construction contours of the Old <br />Refuse Pile, and the locations of Cross Sections AR through HR. Map 6, Disposal Area <br />Topography, depicts the idealized contours of the disposal area near the former location of the <br />Wash Plant upon completion of the Project.. <br />In its present condition, the slopes subject to this project vary in gradient from slightly steeper <br />than 1.5H:1V to just less than 2H:1V, with the majority of the slope averaging about 1.75H : <br />1V. Cross Sections A through H depict the current topography. Upon completion of the <br />project, the gradient of the north slope of the Old Refuse Pile will average 2H:1V. The <br />gradient at any one location may vary between 1.9H:1V and 2.1H:1V, as depicted on Cross <br />Sections AR through HR. A variance in slope gradient which results in any one cross <br />sectional slope being steeper than 1.9H:1V is not permitted. An existing roadway located near <br />the top of the slope to be cut must be maintained throughout the project at a minimum width of <br />twelve feet (12') . <br />North Slope Old Refuse Pile Cut and Fill <br />In some portions of the project area topsoil has been spread over slopes which are at a gradient <br />of 2H:1V. The soil in these less steep locations will be salvaged by CONTRACTOR, and <br />stockpiled at the location noted on Map 3, Project Area. <br />It is estimated that cubic yards of coal refuse material will be excavated from the Old <br />Refuse Pile in order to achieve the specified 2H:1V post construction slope. Of this volume, <br />13 <br />