Reclamation Plan <br />Exhibit E <br />portal is buried under 5 feet or more of cover and graded with slopes equal to or less than the natural <br />slopes which are estimated to be equal to or less than 1(H) to 1(V). Where possible, slopes will be graded <br />to approximate original contour. The post mine topography and reclamation will blend in with the exist- <br />ing topography and vegetation. See: <br />• Figure F -1: May Day No. 1, Affected Acreage 3.5 acres; <br />• Figure F -1A: May Day No. 1 East, Affected Acreage 0.5 acres; <br />• Figure F -2: May Day No. 2, Affected Acreage 3.3 acres; <br />• Figure F -3: May Day No. 3, Affected Acreage 3.2 acres; <br />• Figure F -4: Chief Tunnel, Affected Acreage 0.3 acres; <br />• Figure F -5: Idaho Affected Area, Affected Acreage 8.2 acres; <br />• Figure F -6: New Access Road, Affected Acreage 1.8 acres; <br />• Figure F -6: Base of Operation, Affected Acreage 1.0 acres; <br />• La Plata Bridge: Affected Acreages 0.1 acres; and, <br />• Pre - Existing Roads: Affected Acreage 9.5 acres. <br />Total: 31.4 acres <br />In addition the following final reclamation activities will be undertaken: <br />• Augmentation Pipeline Corridor (0.4 acres) will be reclaimed as presented on Figure F -4; <br />• La Plata River Bridge will remain after mining (0.1 acres); <br />• The base of operation (1.0 acre staging area) reclamation plan is presented with the Road Design <br />drawings at Attachment D -1 and Figure C3.10; <br />• The Idaho mill site (3.1 acres) will be reclaimed as presented on Figure F -4; <br />• The Idaho Pay Day mill site (5.1 acres) will be reclaimed as presented on Figure F -4; <br />• Preexisting Roads (9.5 acres) will remain; <br />• The New Access Road (1.8 acres) reclamation plan is presented with the road design drawings at <br />Attachment D -1. <br />Pre - existing structures (bridges, fences, historical buildings) and roads will not be reclaimed. However <br />the stormwater structures will be repaired or restored to approximate design specifications. <br />Within the augmentation pond at the Idaho Operational Area prior to reclamation, fresh water will be dis- <br />charged to an adjacent drainage channel or spray irrigated on the ground in accordance with CDPHE dis- <br />charge permit and DWR requirements. Upon closure, the augmentation ponds will be backfilled, and <br />graded to blend with the existing topography. Slopes will be equal to or less than 2(H):1(V). Standard <br />revegetation method will then be implemented (Section 6.4.5(2)(d)). <br />After clean up and earthmoving, final revegetation will be conducted as identified in Section 6.4.5(2)(d) <br />and (f). <br />Wildcat Mining Corporation <br />112d Permit — May Day Idaho Mine Complex <br />Revised August, 2011 <br />Exhibit E — Rule 6.4.5 <br />DEN 97,615,521v1 9 -26 -11 <br />Page 4 of 21 <br />