Mr. Wallace H. Erickson <br />Response to August 22, 2011 Cazier Memorandum <br />September 9, 2011 <br />Page 4 <br />BMP #12 Rip Rap <br />Rip rap material is readily available on site. Rip rap will be <br />produced during road construction. D50 riprap, as designed, <br />will be sized using portal crushers and screened as necessary. <br />Crushing and screened activities will be located such that <br />BMPs can be in place to prevent materials from eroding into <br />streams or sensitive areas. Sized materials will be used in <br />place, stored in designated areas (staging, rock storage areas) <br />or piled within the area where the materials will be used as <br />road base or as stone filter. Rip rap as specified will be used <br />for channel aprons (including flare) and channels that extend <br />up the banks and to the height of the maximum depth of flow <br />for the design storm. The maximum riprap diameter size will <br />be dmaX 1.5 d50. The apron thickness will be equal to 1.5 x <br />d The upside end of the apron adjacent to the pipe will <br />have a width three times the diameter of the pipe. The apron <br />will be constructed with no overfall at the end. As necessary, <br />fugitive dust will be controlled using water. <br />Wildcat intends to analyze the gradation, density and shape of riprap created <br />during crushing and screening operations to confirm the riprap specified in the <br />Stormwater Management Plan is appropriate for design conditions. Wildcat will also <br />commit to meeting the design specifications set forth in Section 506 of the CDOT <br />Standard Specifications for Road and Bridge Construction (2011). <br />In order to clarify this intent, Wildcat will add the following bullet after the third <br />bullet in the Pre - Construction Activities section on Page 5 of Attachment D -1 (New <br />Access Road Construction Work Plan): <br />• Perform laboratory testing and visual inspection on terrace rock which will be <br />crushed and screened for use as riprap to determine density and conformance <br />with Section 506 of the CDOT Standard Specifications for Road and Bridge <br />Construction (2011); <br />Wildcat will also add the following sub - bullet to the existing fourth bullet in the <br />Pre - Construction Activities section on Page 5 of Attachment D -1: <br />• Criteria for the design of riprap as specified in work plans and the <br />Stormwater Management Plan; <br />Finally, Wildcat will further clarify its intent by adding the following bullets after <br />the fifth bullet of the Pre - Construction Activities section on Page 5 of the New Access <br />Road Construction Work Plan: <br />DEN 97,591,786v1 9 -9 -11 <br />GREENBERG TRAURIG, LLP • ATTORNEYS AT LAW • WWW.GTLAW.COM <br />