Laserfiche WebLink
Response to Preliminary and Secondary Issues April 28, 2011 <br />Response #2 Geotechnical Stability Response to DRMS-April 18, 2011 Comments <br />The following responds to questions #5 through #18 in the March 7, 2011 Access Road <br />memorandum: <br />question-#5 DRMS March 7rh 2011 Memo File No M-1981 185 <br />In the summary section of the Access Road Repair & Maintenance plan, the Applicant lists the <br />following Pre-Construction Activities: <br />a. Utilizing engineering drawings and topographic features (Sakura Engineering Sheets I <br />thru 16) <br />b. Establish Profile and Cross Section Stakes -for construction purposes (See Sakura <br />Engineering Sheets 8, 9 and 10 of 16 sheets) " <br />c. Establish cut and fill stakes per the engineering drawings (See Sakura Engineering <br />Sheets 1, 2, 3, 4, 8, 9, 10, 11, 12, and 13 of 16 sheets) <br />d. Prepare and submit final as-built drawings. <br />The Applicant mustprovide the Division with a detailed workplan, as requested in the previous <br />Geotechnical review memos, for the proposed Pre-Construction Activities. <br />Response #5.-A detailed access road work plan is included in Attachment F CLC Road <br />Design- Third Adequacy Response The Sakura Engineering road designs have been replaced <br />by the road and base of operation design prepared by CLCAssociates (2011) <br />Ouestion-#6 DAMS March 7rh, 2011 Memo: File No M-1981-185 <br />The required workplan must explain how the Applicant will implement the engineering drawings <br />and topographic features provided in Sakura Engineering Sheets 1 thru 16 to complete <br />construction of the access road. The work plan must also describe how quality assurance and <br />quality control will be documented and certified by a qualified professional engineer registered <br />in the State of Colorado. <br />Response #6. Ouality assurance activities are presented in the access road work plan <br />(Attachment F-CLC Road Design- Third Adequacy Response): <br />Ouestion-#7 DRMS March 7`h. 2011 Memo: File No M-1981-185 <br />The Applicant states, final as-built drawings will be prepared and submitted as part of the pre- <br />construction activities. "Final " as-built drawings of the repairedlreconstructed road cannot be <br />prepared until construction is complete. Please clarify if the Sakura Engineering As-Builts dated <br />October 20, 2009 are considered by the Applicant to be the 'final" as-built drawings to be used <br />for reference as part of the pre-construction activities. <br />Response-Second and Third Geotechnical Issues 2 5/27/2011