Laserfiche WebLink
amecIO <br />Earth & Environmental <br />E) Material Processing <br />1) South Cresson Clay Processing Area <br />Soil Liner Fill production for the VLF was suspended at the South Cresson Clay Processing <br />area because rain had saturated the stockpiles. This Location <br />? () tons Week Cumulative Comments <br />So Cresson Clay Processing 0 40,291 <br />Squaw Gulch Processing - 35,816 Produced and stock filed <br />Total 0 76,107 <br />F) VLF Miscellaneous Structures <br />No work performed during the week. <br />III) Underground Working <br />A) Drilling <br />No work performed during the week. <br />B) Mine Shaft/Stope Remediation <br />No work performed during the week. <br />C) Lateral/Slot Remediation <br />No work performed during the week. <br />IV) Storm Water Management Structures <br />A) Control Structures <br />No work performed during the week. <br />B) Best Management Practices <br />Best Management Practices are being observed throughout the VLF Phase 5 Project. <br />V) VLF Geosynthetics <br />No work performed during the week. <br />CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />AMEC observed placement of structural fill between stations A17+00 (+/-) and A29+00 (+/-), <br />approximately 50 to 400 feet left of centerline <br />AMEC observed the drilling of shot holes on the East Perimeter Road. <br />Sheet 3 of 6 <br />VLF Weekly Report WE 06.06.09.D.doc