amid? <br />Earth & Environmental <br />E) Overburden to Stockpile <br />1) VLF <br />No work performed during the week. <br />F) Cut to Fill <br />1) VLF <br />A CAT 385 excavator and a John Deere 850 excavator were used to excavate structural fill <br />material between stations E14 +00 ( + / -) and E16 +00 ( + / -), approximately 0 to 50 feet right of <br />centerline and between stations J27 +00 ( + / -) and J29 +00 ( + / -), approximately 75 to 100 feet <br />right of centerline. The structural fill material was loaded into CAT 777 haul trucks. <br />Prior to structural fill placement existing fill areas were ripped and frost was allowed to thaw <br />or was removed. Existing fill temperature were monitored and found to be above 32 °F before <br />fill placement. An AMEC representative monitored ambient temperatures on an hourly basis <br />during fill placement. Fill temperatures were monitored during ambient temperatures below <br />32 °F and averaged 39 ° F to 44 °F. <br />Structural fill was placed in the following areas: between stations B 1 +00 ( + / -) and B4 +00 ( + / -), <br />approximately 50 feet left of centerline to 50 feet right of centerline; between stations D1 +00 <br />( + / -) and D4 +00 ( + / -), approximately 0 to 75 feet left of centerline; between stations F1 +50 <br />( + / -) and F3 +50 ( + / -), approximately 0 to 50 feet right of centerline; and between stations <br />J16 +00 ( + / -) and J22 +50 ( + / -), approximately 50 to 75 feet left of centerline. Structural fill was <br />placed in 18" to 24" lifts using various CAT dozers. Each lift was moisture conditioned using a <br />CAT 773 water truck (when necessary) and compacted using a 10 -ton vibratory smooth drum <br />compactor, passing over the entire fill surface at least 4 times (method compaction technique is <br />applicable). <br />Structural fill (processed ore) was placed within the Phase IVa VLF between stations G13 +00 <br />( + / -) and G15 +00 ( + / -), approximately 75 to 150 feet right of centerline. Fill material <br />(processed ore) was excavated from the Phase IVc re- certification area, the old LOB haul road, <br />and the southeast corner of Phase IVa using a CAT 375 excavator loading the material into 40- <br />ton articulating haul trucks. Structural fill was placed using a CAT D -8 dozer in 12" loose lifts <br />and moisture conditioned as needed using a CAT 773 water truck. Compaction was achieved <br />using a 10 -ton vibratory smooth drum compactor. Nuclear density testing was performed with <br />results averaging 95% of maximum dry density. Moisture density relations were obtained in <br />accordance with ASTM D698 -07. Ambient and fill temperatures were monitored and recorded <br />during the placement of the processed ore in this area. <br />Blast pattern drilling was performed between stations E12 +00 ( + / -) and E16 +00 ( + / -), <br />approximately 0 to 50 feet right of centerline using three track mounted drill rigs. Blasting was <br />performed in these areas Monday (11/23/2009) and Tuesday (11/24/2009). <br />G) Material Processing <br />1) South Cresson Clay Processing Area <br />Processing of Soil Liner Fill material continued at the South Cresson Clay Process. A CAT D -8 <br />dozer, a CAT 320 excavator, and a CAT 966 front -end loader were used to process the material. <br />VLF Weekly Report WE 11.28.09.D.doc <br />