amen <br />Earth & Environmental <br />feet right of centerline; and between stations K6+00 (+/-) and K10+00 (+/-), approximately 50 <br />to 100 feet right of centerline. The structural fill material was spread using various CAT dozers <br />in 18" to 24" lifts. Each lift was moisture conditioned using a CAT 773 water truck (when <br />necessary) and compacted using a 10-ton vibratory smooth drum compactor, passing over the <br />entire fill surface at least 4 times (method compaction technique is applicable). <br />Structural fill (processed ore) was placed within the Phase IV VLF, between stations G0+00 <br />(+/-), G12+00 (+/-), B2+50 (+/-), and B4+00 (+/-), approximately 100 to 150 feet left of the <br />"G" centerline. Existing processed ore was placed using a CAT D-6 LGP dozer in 12" loose <br />lifts and moisture conditioned using a CAT 773 water truck. Compaction was achieved using a <br />10-ton vibratory smooth drum compactor. Structural fill placement was observed by an AMEC <br />representative constantly. Nuclear density testing was performed with results averaging 95% of <br />maximum dry density. Moisture density relations were performed in accordance with ASTM <br />D-698-07. Today's placement will achieve more than five feet of cover over the Phase IV <br />geomembrane, allowing haulage using the 40-ton articulating haul trucks <br />Blast pattern drilling was performed in the following areas: between stations A7+00 (+/-) and <br />A10+00 (+/-), approximately 200 to 250 feet left of centerline: between stations H2+00 (+/-) <br />and H4+00 (+/-), approximately 0 to 50 feet right of centerline; and between stations J26+00 <br />(+/-) and J27+50 (+/-), approximately 0 to 50 feet right of centerline using two track mounted <br />drill rigs. Blasting was performed in these areas Tuesday (10/6/2009), Wednesday (10/7/2009), <br />and Thursday (10/8/2009). <br />H) Material Processing <br />1) South Cresson Clay Processing Area <br />Processing of Soil Liner Fill material resumed at the South Cresson Clay Process. A CAT D-8 <br />dozer, a CAT 320 excavator, and a CAT 966 front-end loader were used to process the <br />material. <br />Location This Week <br />(tons) Cumulative <br />(tons) Comments <br />So Cresson Clay Processing 5,360 98,913 <br />Squaw Gulch Processing 0 35,816 Processing in area complete. <br />Total 5,360 134,729 <br />I) New ADR Water Tank and Crusher Waterline <br />No work performed during the week. <br />J) Miscellaneous <br />Removal of the old solution lines was finished by cutting the welds in the lines using an <br />oxy/acetylene cutting torch. <br />Removal of the old power poles was performed throughout the week. <br />VLF Weekly Report WE 10.10.09.1)