AM& <br />ame <br />Earth 8 Environmental <br />2. LOB/Delivery Road <br />Removal of cut from Station 30+00 advancing down station to 16+00(+/-). All <br />excavated rock this week has been hauled to Dump 4 using 4 Cat 777 Haul <br />Trucks a Komatsu 800 excavator aided by a Cat D-10 dozer. <br />Rockbreakers continue drilling the LOB/Delivery Road cut from Station 25+00 to <br />Station 29+00 for the planned blasting. Blasted 3-days this week on the <br />LOB/Delivery Road cut. <br />D. Cut to Fill <br />1. LOB Pad <br />No Activities. <br />2. LOB/Delivery Road <br />No fill was placed this week. <br />Night work, and day work consisted of cut from Station 8+00 to approximately <br />4+00 and fill to VLF Station K4+00 to K8+00, 0- to 100-feet left. <br />E. Subgrade Preparation <br />1. LOB Pad <br />No Activities <br />F. SLF Processing (Material is being generated/processed for the LOB and the VLF) <br />The SLF clay plant, located in Dump 5, was down most of the week with limited <br />production. A new plant is due to arrive during the week ending March 23ra <br />Summarv of SLF Drocessin2 <br />Location This Week <br />(tons) Cumulative <br />(tons) Comments <br />LOB Plant, Dump 5 Clay 3,001 23,600 Plant ran at limited production this <br />Processing week. Down 2 days. <br />Totals 3,001 23,600 <br />G. Miscellaneous <br />Fill placement and access for power pole re-location is on going. Sites are outside the <br />immediate LOB/Delivery Road work areas. <br />Work has begun on the foundation preparation for the transfer towers for the planned new <br />conveyor line to the LOB/Pad. <br />Sheet 2 of 11 <br />LOB Weekly Report WE 03.14.09.D