.amecl* <br />Earth & Environmental <br />LOB EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ LOB <br />Date: 3/14/09 <br />Reporting Period: 03/08/09 through 03/14/09 <br />Days S M T W T ` F S <br />Work Shifts D D D D D - <br /> - N N N N N - <br />D = Day Shift N = Night Shift <br />Project No.: 8420125EO <br />Contractor: Ames Construction Co. Inc. <br />There was no night work performed on the LOB this past week. <br />Ambient Temperature Range (F): Low: 9°to 18° High: 28° to 30° <br />Snow on Tuesday AM with high winds and blowing snow. Friday cloudy, fog, light snow <br />the remainder of the week was cool with moderate winds and mostly clear to partly cloudy. <br />AMEC CQA Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: No delays due to weather this week. <br />CONSTRUCTION ACTIVITIES AND PROGRESS: <br />In general, <br />1. EARTHWORKS <br />A. Clear and Grubbing <br />1. LOB Pad <br />Minor clean-up work and removal remains to be completed around the abandon <br />mine working # 19. <br />2. LOB/Delivery Road <br />Work is complete <br />B. Stripping <br />1. LOB Pad <br />Stripping is complete <br />working #19. <br />Minor cleanup to waste remains around the abandon mine <br />2. LOB/Delivery Road <br />Stripping is complete. Minor cleanup to waste remains. <br />C. Waste Rock to Stockpile <br />1. LOB Pad <br />A Cat 325 and Komatsu 800 excavators were used in the pad area for removal of <br />all shot rock to Dump 4. Haul to waste with four Cat 777 haul trucks. <br />Sheet 1 of 11 LOB Weekly Report WE 03.14.09.1)