Colowyo C-1981-019 <br /> 19 February 2009 <br /> Pg 3/4 <br /> Hydrologic Balance (cont.): - Sump 4 contained water approximately one foot below <br /> the top and was not discharging at the time of the inspection. The sump was stable <br /> at the time of the inspection. <br /> - Sump 5 contained water to the top of the sump but did not appear to be <br /> discharging at the time of the inspection. The sump appeared to be stable at the <br /> time of the inspection. <br /> Backfilling and Grading: - Colowyo has committed to provide two reclamation <br /> schedules for the East Pit closure. The first plan is a short term plan that will <br /> encompass the area around the Prospect ditch, including the sump area that is part <br /> of the ditch which is not yet to final grade. This short term plan, in the form of a <br /> Technical Revision JR-78), was received by the Division on 24 December 2008. The <br /> Division has sent Colowyo a preliminary adequacy Letter on this revision. The second <br /> plan is a long term plan that will provide a comprehensive reclamation schedule for <br /> the remaining East Pit, including the closure of the final pit. This long term plan is due <br /> to the Division no later than 31 March 2009. <br /> - Colowyo has been performing some reclamation work with the 101 dragline on the <br /> highwall of the East Pit (although it was not operating at the time of the inspection). <br /> The dragline has moved from the position it has been in for several months. <br /> - The operator was performing Backfilling operations in the Section 4 area of the West <br /> Pit at the time of the inspection. The operator was loading spoil from a temporary <br /> pile with a loader and dumping it along the east edge of the pit just above the East <br /> Taylor Pond. This material was then being pushed into the pit by a D11 dozer. A very <br /> small portion of the area has reached final contour. The area that has been <br /> backfilled has advanced around 100 feet from the last inspection. Please see the <br /> pictures at the end of this report. No other backfilling operations were being <br /> performed in the West Pit. <br /> General Mine Plan Compliance: - The 101 dragline is on the East Pit highwall where it <br /> was waiting to performing reclamation (although it was not running at the time of the <br /> inspection it has performed reclamation work since the last inspection and it has <br /> moved farther east). <br /> - The 102 dragline was working on the west side of the West Pit doing pull-back work. <br /> - The 103 dragline was out of service for scheduled maintenance. <br /> - The 114 shovel operation was working on removing A-Seam overburden in the West <br /> Pit. <br /> - The 115 excavator was idle at the time of the inspection as the operator was not <br /> doing any overburden or coal removal in the South Taylor Pit. <br /> - The mining at the Colowyo Mine appears to be progressing as discussed and <br /> approved in the PAP. <br /> Fish and Wildlife: There was a herd of elk (approximately 30) on the topsoil pile across <br /> from the facilities area and there was another small herd (approximately 50) on the <br /> East Pit reclaim. There were two bald eagles seen in the Taylor Draw area. <br />