Laserfiche WebLink
6.03 CONSTRUCTION MONITORING AND TESTING: <br />The CQA Monitor shall monitor and test all geosynthetic components of the construction to verify that <br />the construction is in compliance with the project SPECIFICATIONS. The CQA Monitor shall <br />identify inadequate construction methodologies or materials which may adversely impact the <br />performance of the facility being constructed and existing structures. Visual observations throughout <br />the construction process shall be made to ensure that the materials are placed to the lines and grades as <br />shown on the DRAWINGS. <br />The CQA monitor shall review the following submittals by INSTALLER during the project: <br />• verification that a qualified land surveyor has verified all lines and grades; and <br />• subgrade surface acceptance certificates for each area to be covered by the lining system, <br />signed by the INSTALLER. <br />The CQA Monitor shall: <br />• Inspect all geosynthetic materials delivered to site. The CQA Monitor shall document <br />any damage and notify MANAGER; <br />• obtain geosynthetic packaging identification slips for verification and generation of an <br />on-site materials inventory; <br />• observe subgrade conditions prior to geosynthetics installation and verify that any <br />deficiencies, as defined in Section 02200 of the SPECIFICATIONS, are corrected; <br />• observe permanent anchoring of geosynthetics to verify that design and project <br />SPECIFICATIONS are met; <br />• observe that required overlap distances are met; <br />• monitor and record ambient air temperatures; <br />• verify that no continuous horizontal seams are placed on slopes unless approved by <br />CERTIFYING ENGINEER; and, <br />• observe and document that all soil materials placed on top of the geosynthetics are done <br />in such a manner as to ensure that the geosynthetics are not damaged. <br />6.03.01 GEOMEMBRANE: <br />During geomembrane installation, the CQA Monitor shall observe and document deployment, trial <br />seams, field seaming, non-destructive and destructive seam testing, and repairs to assure that the <br />installation is in compliance with the SPECIFICATIONS. <br />Deployment - The CQA Monitor shall verify that only approved materials are used, each <br />panel is given a unique panel number, no geomembrane is placed during unsuitable weather <br />conditions as outlined in Section 02776, Article 1.05 of the SPECIFICATIONS, the <br />geomembrane is not damaged during installation, and anchoring is performed in compliance <br />with the SPECIFICATIONS and design DRAWINGS. The CQA Monitor shall record the <br />deployment on the deployment log form. <br />Section 01400.2 Page 6 of 10 March 22, 2000 <br />Geosynthetic CQA Plan Golder Associates Revision 5 <br />1:\072140\0100VRJFRISOLATI0NBA2R-15M YOM 2CQA GFASYMI'HEE'1'ICS.pOC