Laserfiche WebLink
MEASUREMENT AND PAYMENT <br /> See 1.0 Mobilization/Demobilization, attached. <br /> Task 2 - Linden Avenue Coal Loadout <br /> The purpose of this task is to remove and dispose of coal, coal fines and other imported <br /> rock from portions of a six-acre industrial site previously used as railroad coal load out. The <br /> work will include grading, so that drainage is away from the A.T. & S.F. railroad tracks, and <br /> revegetation of a portion of the site, near the Baca Ditch. <br /> Work Description <br /> The area containing coal to be removed comprises some four (4) acres, and extends <br /> approximately 950 feet north of Linden Avenue, between the A.T. & S.F. Railroad tracks <br /> and Baca irrigation ditch. Coal depth varies between 4 and 31 inches as shown by thickness <br /> contours on Map #3. Coal and other imported rock will be removed to a depth sufficient <br /> to obtain a 1% grade away from the railroad tracks. Grading shall begin six (6) inches from <br /> the ties at their bottom elevation. This will cause surface water to collect in a swale located <br /> west of and paralleling the Baca ditch. Near the railroad tracks the bottom of the coal layer <br /> to be removed is marked by the presence of red limestone ballast, otherwise natural soil is <br /> present. Removed material is,,Io be disposed of atthe City of-Trinidad landfill located on <br /> Indiana Street, approximately, 2 miles from the loadout,� the­ffiumcipal power plant , <br /> located on U.S. 160=135, near 4he-north city limit of Trinidad;-one-mile-from.the loadout. �> <br /> The general location of a sewer manhole is shown on Map #3. The contractor is <br /> responsible for locating all above and below surface utilities and protection of same from <br /> damage. The Baca ditch is an active irrigation ditch and is not to be filled or otherwise e j�f <br /> interfered with. <br /> l Gv�c� <br /> Revegetation of the disturbed area will be limited to a 100 foot wide section paralleling the <br /> Baca ditch. �✓ <br /> Measurement and Payment <br /> There will be no measurement for payment for Task #2. Payment for Task #2 will be <br /> reflected in a lump sum bid under Item #2 on the Bid Schedule. <br /> Task 3 - Section 15 Stream Realignment <br /> This task requires the furnishing of all labor and equipment necessary to excavate and <br /> establish a new stream channel for an unnamed stream emptying into Del Augua Creek in <br /> the extreme south center of Section 15. <br /> Work Description <br /> Approximately four hundred feet of new stream channel will be excavated through surficial <br /> clay, silt, and unconsolidated sediment containing occasional coal, and other imported rock. <br /> Bedrock is believed to be between five and ten feet below the surface, and consists of silt <br /> 8 <br /> l " <br />