There will be no measurement for Task #7. Payment for Task #7 will be reflected in a <br /> lump sum bid under Item #8 on the Bid Schedule. <br /> Task #8 - Spillway Removal Pond 22-P4. <br /> Scope of Work and Work Description <br /> The emergency spillway shall be removed from Pond 22-P4, allowing free flow around the <br /> embankment. Care must be taken to not disturb portions of the embankment where ' <br /> vegetation is well established. Additionally a 10-foot section of Ditch 22-1310, shall be <br /> removed, and flow directed into Pond 22-P4. <br /> Measurement and Payment <br /> There will be no measurement for Task #8. Payment for Task #8 will be reflected in a <br /> lump sum bid under Item #8 on the Bid Schedule. <br /> Task 9 - Ditch and Gully Repair <br /> Work Description <br /> Approximately 100 feet of the failed ditch to Pond 15-P shall be removed (filled) and <br /> graded to original contour. The large adjacent gully re ulting from this failure shall be 1 <br /> repaired by creating a gentle swale 3 feet deep contaimn riprap. The riprap material must <br /> consist of durable irregular rock having a minimum D-50 of 6 inches and a D-max of 9 ' <br /> inches. Riprap will have to be imported (s@o P-avvie- 434 <br /> There will be no measurement for Task #9. Payment for Task #9 will be reflected in a <br /> lump sum under item #9 on the Bid Schedule. <br /> Task 10 - Spillway Repair <br /> Work Description <br /> The emergency spillways of Ponds 15-P11 and 15-P12 shall be lowered one and one-half <br /> (1 1/2) feet to accommodate a total of 3 feet of riprap. Riprap material must consist of <br /> durable irregular rock having a minimum D-50 of 6 inches and a D-max of 9 inches. Riprap <br /> will have to be imported (see Drawing #3). <br /> Measurement and Payment <br /> There will be no measurement for Task #10. Payment for Task#10 will be reflected under <br /> Item #10 on the Bid Schedule. <br /> Task 11 - Riser Modification <br /> Work Description <br /> 11 <br />