~• V <br />TIME SCHEDULE <br />Extraction operations and reclamation of the site ere anticipated to be <br />complete in eight years. It is anticipated that mining operations will start <br />October 1, 1986. Extraction in Area 1 will be completed in approximately <br />three years end Aree 2 in three years. Reclamation of Areas 1 and 2 will <br />begin after extraction is complete in these areas. Final reclamation of Aree <br />2 is anticipated to be completed two years after extraction is complete in <br />thls Brea. <br />