Phase IV Weekly Summary No. 30 Page 2 <br />footprint, where the Arequa gulch sedimentation pond will later be constmcted. <br />003-2203 <br />• Ames also began fill placement and compaction efforts associated with the construction of the Phase <br />IVa southern access road, south of the IVa liner construction limits. A Caterpillaz D10 cut from a <br />local borrow above the fill, down into lifts approximately 12" in thickness. A Mack Tandem axle <br />water truck provided moisture conditioning of the fill when required, and a Caterpillar 563C <br />distributed compactive effort across the fill azea. <br />Ames conducted slope re-contouring in the Phase IVa azea, which included blasting east of the <br />existing HWY 67, at Permanent Diversion Channel stations 34+00 through 44+00 on August 27`s <br />through 30`x. <br />Confirmation drilling was performed on underground working UG-472; boreholes 1 through 21, <br />with no discovery of additional workings. The boreholes were grouted on August 30u'. Excavation <br />was performed ornAugust 30a' on underground workings UG-462 through dJG-472 by use of a <br />Caterpillaz 330B track-hoe. Of these workings, UG-462 through UG-471 were immediately <br />backfilled and compacted as no working was encountered during the excavation (most workings <br />were dug only a few feet into solid rock). <br />Phase IVb <br />Ames completed placement and compaction efforts of SF, west of the active crasher, for the new <br />LOB construction subgrade. A Caterpillaz D8 dozer was used in the azea to perform rough grading <br />of the southwest facing inboazd side slope, and the top surface of the fill. A Caterpillaz 563C <br />vibratory roller performed compaction activities on the top and side slope of the fill. A Caterpillaz <br />D8 dozer had to rip the top surface on several occasions during this reporting period in order to <br />facilitate drying after precipitation events, then re-roll the fill to grade. The water wagon and/ or the <br />Mack water truck attained moisture conditioning when necessary. <br />Confirmation drilling was performed on underground working EI-Point, Boreholes 10 and 11, to <br />delineate an anomaly discovered within the working when it was previously drilled. No additional <br />workings were identified, completing the drilling program for the working. The boreholes were <br />grouted on August 30u'. <br />Phase IVc <br />Ames did not perform any cut or fill activities within the Phase IVc areas during this reporting <br />period. <br />Confirmation drilling was performed on underground working UG-294B (in which the drilling <br />program on this working began several weeks prior), boreholes 13 through 26. To date, no borehole <br />on this working identifies additional workings. The boreholes drilled this week were grouted on <br />August 30~'. <br />(See Attachment A for approximate construction locations for all Phase IV azeas.) <br />e~w. rv.3u wszss~wi.m~ Golder Associates lnc. <br />