<br />5~ <br />Exihibit E, I, J, K <br />Reclamation Plan <br /> <br />Kirkland Construction will follow the attatched SCS recommendations for reclamation of this site. <br />Measures will be taken to minimize disturbance to the hydraulic balance during mining operations. <br />Storm water control devices, sediment basins, and silt fences will be ut$ized within the areas being <br />disturbed in the locations where water will be eating the mined property. Control measures will be <br />installed and maintained prior to ground disturbance, during mining and reclamation. <br />The existing access road will remain. The new access road will be left in place after mining. <br />The pond will be relocated as indicated in the 111 permit. <br />~~ g~ u <br />~" <br />J~`yPFN <br />~~ <br />The appro~dmate areas in each phase to be mined is 50 acres, no more than 40 acres at a time will be <br />disturbed before reclamation will be completed on previously disturbed areas. <br />