My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
PERMFILE118180
DRMS
>
Back File Migration
>
Permit File
>
200000
>
PERMFILE118180
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 10:13:52 PM
Creation date
11/25/2007 4:51:27 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1977036
IBM Index Class Name
Permit File
Doc Name
APPLICATION FOR MINING & RECLAMATION PERMIT
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
51
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
r <br />SECTION C - MINING AND RECLAMATION PLAN <br />Mining of the proposed property is proposed to be <br />accomplished over a thirty-five (35) year period from <br />nine areas-phases as noted on the Mining Plan. The mining <br />duration of each phase area will vary from two and one-half <br />(2-1/2) to five (5) years with Area 9 taking possible five <br />(5) to eight (8) years to complete, because of its larger <br />acreage. <br />It must be emphasized that a concurrent reclamation <br />is to take place with the ongoing mining activity for each <br />phase-area. <br />The first step - Phase One (same procedures apply to <br />subsequent areas) will be the removal and temporary proper <br />storage of topsoil, and overburden material. The locations <br />of sand and gravel plant, the redi-mix plant, office and <br />shop will be as noted on the Mining Plan and aerial photo. <br />The sound attenuation characteristics will be continu- <br />ously improved, by strategic location of stockpiled material, <br />as noted on the Mining Plan. <br />The actual gravel extraction process will commence in <br />Phase One area, with the same process to continue in follow- <br />ing phases. The method of extraction will be with a <br />dragline, after the dewatering process utilizing a centri- <br />fugal pump, has taken place. After the sand and gravel <br />has been dug from the pit by the dragline, it is then taken <br />to the crushing and processing plant and delivered to the <br />customer or stockpiled for future use. <br />Reclamation, starting with the first phase until final <br />completion, will be an ongoing process with backfilling and <br />contouring of the land as part of the mining operation. <br />Final reclamation of each phase with grassing and tree plant- <br />ing to take place immediately upon completion of each phase. <br />For completion revegetation program, see Section G - <br />Soils and Vegetation. <br />~,. <br />G <br />,. <br />-3- <br />
The URL can be used to link to this page
Your browser does not support the video tag.