<br />• e. We plan to divide the 77 acres into 8 phases of 10 acres or less. As soon <br />as a sufficient amount of area is available, that will not interfere with <br />mining and processing, backsloping and the replacement of topsoil will <br />begin. Seeding will begin when the area is safe from operational <br />intrusion and when the area becomes large enough to be economic. <br />Any seeding will take place in the late fall. <br />i. We have 77.65 acres less 2 acres for a live snow fence area along <br />Hwy 112 which leaves 75.65 acres that will be divided into 8 <br />phases. With each phase taking approximately 15 years to <br />complete, for a total of approximately 120 years or more. <br />ii. Approximately 10 acres will be mined at any one time. <br />iii. Phase i thru phase 8. Each phase will be reclaimed at fts <br />completion. <br />F. See encbsed map. <br />G. Sand and gravel will be extracted for the use of manufacturing concrete <br />and asphalt. <br />H. There will not be any incidental products. We have a use for all material <br />manufactured from this pit: Road base, sand, gravel, and manufactured <br />fines. <br /> <br />