C. Reclamation <br />• 1. Spoil Grading (Out of Area) <br /> 10 acres = 10 hrs <br /> 1 acre/hr <br /> 10 hrs X $68.01 = $ 680.00 <br /> 2. Topsoil Redistribution <br /> 24,200yd3 = 17 hrs <br /> 1,444 LCY/hr <br /> 17 hrs X $102.99 = $ 1,751.00 <br /> 3. Revegetation <br /> 10 acres X $611/acres = $ 6,110.00 <br /> $ 65,515.00 <br /> V. Area 51W <br /> A. Site Preparation <br /> 1. Topsoil Salvage <br /> 14,520yd3 = 10 hrs <br />• 1,444 LCY/hr <br /> 10 hours X $102.99/hr = $ 1,030.00 <br /> 2. Spoil Grading (Into Area) <br /> 6 acres = 6 hrs <br /> 1 acre/hr <br /> 6 hrs X $68.01 = $ 408.00 <br /> 3. Material Haul to Area 51 <br /> 6960 yd3 = 6.8 hrs <br /> 1,026 yd3/fleet hr. <br /> 6.8 hrs X $169.50 X 3 = $ 3,457.80 <br /> B. Riprap and bedding haul placement <br /> 1. Riprap <br /> 1265yd3 X $40/yd3 = $ 50,600.00 <br /> 2. Beddiny <br /> 395yd3 X $18/yd3 = $ 7,110.00 <br />• <br /> - 49 - P.evised 07/29/88 <br />