~'~, 2.13 RECLAMATION SCHEDULE <br />` Reclamation will proceed after mining has ceased. Regrading of the <br />• mine bench, facilities, and sediment pond areas will require 4 weeks; topsoil <br />respreading will require a total of 3 weeks; seeding and mulching with erosion <br />control blanket will require 2 weeks. <br />Fertilization of the whole azea mill require about 3 days. Seeding will occur in <br />September or October+ <br />The mine bench reclamation sequence will be topsoil removal, topsoil <br />storage, topsoil respreading, phosphate fertilization, topsoil compacting, seeding, <br />mulching, and nitrogen fertilization and shrubstock planting. <br />-- -tea <br />All revegetation will take place during September 1 <br />to November 1 time period except if weather forces a <br />• spring planting. The seed mixes have been changed as <br />requested. Any seed that is broadcasted will be <br />applied at twice the rates presented. Cover crops <br />will not be used as a form of mulch, and straw will <br />be applied at a rate of 3,000 lbs/acre. <br />~ - --~ - - <br />~ ~ . <br />i <br />• <br />M-11 <br />- ~h~'~'~ <br />