• Exhibit Page 11 • <br />of up to 50 by 600 feet and up to 15 feet deep will be excavated (connecting to <br />the sediment basin) to improve drainage and transport sediment to the basin. <br />During Year 2, Stockpiles S6 and S7 will be built. <br />In Year 3, mining of the north end of the upper level will be done, stripping and <br />mining an area of 1.67 acres. After stripping 2 feet of soil, raw material will be <br />removed at a depth of from 6.9 to 8.4 feet (8.9 to 10.4 feet below original ground <br />level). The processing plant will be set up approximately 500 feet north of the <br />previous year's location, and will use raw and finished products as berms to <br />reduce noise to the south. The drainage ditch wi{I be extended 580-600 feet <br />further north to improve drainage and transport sediment to the basin. During <br />this phase of Year 3, Stockpiles S8 and S9 will be built, completing the enclosure <br />of the site. <br />MINING OF THE LOWER LEVEL <br />In the rest of Year 3, the southeastern corner and southern edge of the lower <br />level will be mined. Mining will be done around the edges of the sediment basin <br />and ditches constructed during years 1, 2 and 3. This will be done either by <br />backhoe, working from the top of the face and expanding the open water <br />surface, or by dewatering the pit and using loaders. Dewatering, when required, <br />will pump water either into the preexisting pipe or by surface-laid flexible piping to <br />discharge into the Dolores River in accordance with the SWMP. During this <br />second part of Year 3, approximately 3.5 acres (already disturbed by previous <br />activities) of the lower level (including the ditch) will be mined. Waste materials <br />will be placed near Stockpile S10 at the south edge, backfilling and beginning <br />reclamation for the permanent ponds. The processing plant will remain in the <br />same general location during this portion of Year 3. <br />In Year 4, mining of the eastern and central portions of the lower level will be <br />done, mining an already-disturbed area of 5.3 acres. The processing plant will <br />remain in the same general location as during Year 3. Raw material will be <br />removed at a depth of approximately 20 feet below the original ground surface. <br />During Year 4, waste materials will be added to Stockpile S10 or to backfill <br />locations as part of the shoreline of the South and Middle Ponds. This may allow <br />some finish reclamation grading, spreading of topsoil, grading, preparation and <br />seeding to take place on the south end of the permit area, as well as along the <br />eastern edge of the permit, in Year 4. This may allow early removal and use of <br />materials in Stockpiles S3 and S4, which may be screened to recover gravel <br />before placement. <br />In Year 5, mining of the northern and northwestern portion of the lower level will <br />be done, mining an already-disturbed area of 5.3 acres. The processing plant will <br />be set up at much the same location as in Year 4, although excavation of the <br />material at that location and stockpiling for processing will be done prior to plant <br />set-up for the year. Raw material will be removed at a depth of approximately 20 <br />feet below the original ground surface. During Year 5, waste material will <br />continue to go to Stockpile S10 or backfilled as part of the shoreline of the <br />Four States Aggregates, LLC 30 DEC 2000 <br />iApplication for Permit: Line Camp Pit FSA-LCP-D1-001 <br />