topsoil dist. cost. summary
<br />• COLOWYO COAL COMPANY
<br />2000 MID TERM REVIEW - TR - 51
<br />TOPSOIL DISTRIBUTION COSTS
<br />SUMMARY OF COSTS
<br />Ecuioment by Areas
<br />Scrapers
<br />East Pit Summary '
<br />627E Suapers
<br />West Pit Summary
<br />627E Suapers
<br />Section t6
<br />627E Suapers
<br />Facilities
<br />627E Scrapers
<br />REVISED FEBRUARY 15, 2001
<br />Loose Bank Hours Cost Total
<br />Yards Yards by Equip per Hour Cast
<br />(Lcy) (ecy) (hours) ($Ihr.) ($)
<br />117,675 102,500 522 $121. 35 $63,293
<br />0 0 0 $0 .00 $0
<br />291,654 253,612 1,188 $121 .35 $144,125
<br />620,264 539,360 2,260 $121 .35 $276,714
<br />• Subtotal Topsoil Distribution Scrapers 1,029,793 095,472 3,990 $121.35 $404,131
<br />Haul Trucks
<br />East Pit Summary
<br />777 Haul Trucks 1,450,288 1,261,120 5,400 $159.39 $860,641
<br />992C Loader 1,450,288 1,261,120 1,733 $184.32 $319,375
<br />D10N 1,450,288 1,261,120 1,949 $168.27 $328,011
<br />Wesl Pit Summary
<br />777 Haul Trucks 1,333,419 1,159,495 3,347. $159.39 $746,511.81
<br />992C Loader 1,333,419 1,159,495 1,100 $184.32 $293,638.99
<br />D10N 1,333,419 1,159,495 1,162 $168.27 $283,301.08
<br />Section 16 Pit Summary
<br />777 Haul Trucks 134,992 117,384 605 $159.39 $96,486
<br />992C Loader 134,992 117,364 161 5184.32 $29,727
<br />D10N 134,992 117,384 101 $168.27 $30,531
<br />Facilites Summary
<br />777 Haul Trucks 226,212 196,706 1,242 $159.39 $196,021
<br />992C loader 226,212 196,706 270 $184.32 $49,815
<br />D10N 226,212 196,706 286 $168.27 $48,061