topsoil dist. cost. summary
<br />• COLOWYO COAL COMPANY
<br />2000 MID TERM REVIEW - TR - 51
<br />TOPSOIL DISTRIBUTION COSTS
<br />SUMMARY OF COSTS
<br />Eouioment by Areas
<br />Total Haul Trucks
<br />777 Haul Trucks ~'
<br />992C Loader
<br />D10N
<br />•
<br />•
<br />Subtotal Topsoil Distribution Haul Trucks
<br />Road Maintenance
<br />East Pit Summary
<br />14G Motorgrader
<br />5000 Gallon WaterTrudr
<br />West Pit Summary
<br />14G Motorgrader
<br />5000 Gallon Water Truck
<br />Section 16 Pit Summary
<br />14G Motorgrader
<br />5000 Gallon Water Trucc
<br />Facilities Summary
<br />14G Motorgrader
<br />5000 Gallon Water Truck
<br />Total Road Maintenance
<br />14G Motorgrader
<br />5000 Gallon Water Truck
<br />REVISED FEBRUARY 15, 2001
<br />Loose Bank Hours Cost Total
<br />Yards Yards by Equip per Hour Cost
<br />(Lcy) (Bq) (hours) ($Ihr.) ($)
<br />3,144,911 2,734,705 11,931 $159.39 $1,901,660
<br />0 0 3,757 $184.32 $692,557
<br />0 0 4,100 8168.27 $689,904
<br />3,144,911 2,734,705 19,788 $165.96 53,284,120
<br />1,568,168 1,363,624 2,240 $59.80 $133,966
<br /> 2,240 $48.58 $108,831
<br />1,333,419 1,159,495 550 $59.80 $32,881
<br /> 550 $48.58 $26,711
<br />284,455 247,352 146 $59.80 $8,719
<br /> 146 $48.58 $7,003
<br />816,346 709,866 421 $59.80 $25,190
<br /> 421 548.58 $19,871
<br />4,002,308 3,460,337 3,357 559.80 $200,756
<br />3,357 $48.56 $162,496
<br />Subtotal Topsoil Distribution Road Maintenance 4,002,388 3,480,337 6,714 $363,252
<br />S~~mmarv o~quioment by Tvoe
<br />777 Haul Trucks
<br />992C Loader
<br />D10N Dozers
<br />627E Scraper
<br />14G Motorgrader
<br />5000 Gallon Water Truck
<br />Total Topsoil Distribution Costs
<br />3,144,911 2,734,705 11,931 $159.39 $1,901,660
<br />3,144,911 2,734,705 3,757 $184.32 $692,557
<br />3,144,911 2,734,705 4,100 $168.27 $689,904
<br />1,029,793 895,472 3,990 $121.35 $464,131
<br />4,002,388 3,480,337 3,357 $59.80 $200,756
<br />4,002,388 3,480,337 3,357 $48.56 $162,496
<br />
<br />18,469,300 16,060,261 30,492 $4,131,503