2.0 STRUCTURAL DEMOLITION AND REMOVAL <br />2.1 Description <br />This specification covers all work required to demolish, raze, or otherwise <br />dismantle and dispose of all structures, facilities, and utilities listed <br />under item 2.2.C below. Structures and facilities are generally depicted on <br />Exhibit 3A. The Coal Preparation or Wash Plant is depicted on Exhibits 6A <br />through 6E. This specification also covers the removal and disposal of all <br />mining related equipment, materials, parts, supplies and garbage remaining <br />within the working area limits of the East mine area. The working area limits <br />are delineated on attached Exhibit 3A. <br />2.2 Execution <br />A. Salvage <br />The CONTRACTOR is allowed salvage rights to all mining related <br />structures, facilities, parts, supplies and materials remaining within <br />the East mine working area limits. Exceptions to salvage rights consist <br />of the Delta Montrose Electric Association (DMEA) power line and items <br />associated with the highway right of way such as signs and markers. <br />The OWNER does not represent or guarantee that any of the items remaining <br />on the project site at the time of the pre-bid meeting will be on the <br />site at the time structural demolition and removal operations begin. The <br />OWNER is not responsible for any subsequent unauthorized removal from the <br />site, movement of, or damage to any of the structures, facilities and/or <br />mining related materials which were in place at the time of the on-site <br />pre-bid meeting. The CONTRACTOR shall understand that the dollar amount <br />bid for demolition and removal of each item listed in the bid schedule <br />shall consist of the total cost of demolition or dismantling plus removal <br />or disposal and less the anticipated value of salvageable items that are <br />anticipated to be on the site at the time structural demolition <br />operations begin. No additional payment will be made above the price bid <br />on account of any salvageable portions of structures or other salvageable <br />items having been removed, moved around, or damaged. <br />B. Demolition and Removal Performance Standards <br />The CONTRACTOR shall demolish or dismantle, remove from the mine site if <br />salvaged, or dispose of on site or at the refuse disposal area all of the <br />structures, facilities and materials described in Section 2.2.C below, <br />and in accordance with the following performance standards: <br />1. Removal - The CONTRACTOR shall remove all above grade portions of <br />eacF~escribed structure, including all inside contents and any <br />other items affixed to or associated with the structure. In no case <br />shall any materials be left on the surface of or outside the working <br />area limits, unless authorized by the PROJECT MANAGER. <br />-6- <br />