3.3 Execution <br />The CONTRACTOR shall construct a solid concrete block wall in the <br />configuration shown on attached drawing sheet 9 of 9. A level trench or <br />keyway for the first course of concrete blocks shall be excavated a <br />minimum of 16" into the floor of the entry, or to competent rock if <br />encountered less than 16" below the present floor elevation. ALL <br />material excavated from the keyway trench shall be completely removed <br />from the mine opening and away from the mine drainage channel. The back <br />or rear portion of the wall shall be placed against the existing 6" x 6" <br />vertical wall and horizontal roof timbers, and the wall shall be <br />constructed to contact both wood plank side walls and the wood plank <br />roof. All voids remaining between the roof, walls, floor and the <br />concrete blocks shall be filled with grout. The CONTRACTOR shall install <br />three drainage pipes within the wall between the second and fourth <br />courses as shown on the attached drawing. The ends of each segment of <br />pipe shall be cut to set flush with the front and rear wall faces, and <br />all voids remaining between the pipe and concrete blocks shall be filled <br />with grout sufficient to prevent any water from passing between the <br />installed pipes and concrete blocks. Masonry units shall be laid plumb, <br />level and true to line in full beds of mortar. Joints shall be made in <br />block work uniform and not more than 3/4 inch wide. After becoming <br />"thumb-print" hard, joints exposed shall be tooled to a weather joint. <br />Mortar placement shall be discontinued when the air temperature reaches <br />40°F and is falling and shall not be resumed until the air temperature <br />reaches 35°F and is rising. No mortar shall be placed on based course <br />containing frost or other frozen material. A 6 ft. long wood plank with <br />a minimum cross sectional size of 3"x6" shall be bolted vertically to <br />each side wall of the mine opening immediately in front of the <br />constructed block wall, with minimum 6" long wood bolts on 12" centers. <br />ALL voids remaining between the wood planks and the block wall shall be <br />filled with grout. <br />Mortar shall be machine mixed in an approved type of mixer in which the <br />quantity of water can be accurately and uniformly controlled. The mixing <br />time shall be not less than five (5) minutes, approximately two (2) <br />minutes of which shall be for mixing the dry materials and not less than <br />three (3) minutes for continuing the mixture after the water has been <br />added. For work requiring only small batches of mortar or grout, it may <br />be mixed by hand in a water tight mortar mixing box. The materials for <br />each batch shall be well raked and turned over together before the water <br />is added, until the material is an even color throughout the mass, after <br />which the water shall be gradually added until a throughly mixed mortar <br />of the required plasticity is obtained. All mixing boxes and equipment <br />shall be kept clean. Mortars shall be prepared in batches or volume that <br />will be used before initial set takes place, and in no case longer than <br />45 minutes before delivery to mason's mortar board at point of use. <br />Retempering will not be permitted. <br />3.5 Measurement and Payment <br />No measurement for payment shall be made for ventilation entry mine seal <br />construction. Payment shall be made for the lump sum bid price <br />established on the Invitation and Bid Form. The price bid shall include <br />all of the CONTRACTOR'S cost of whatever nature to furnish materials, <br />prepare the mine opening, and construct the concrete block wall and <br />drainage pipes. <br />-8- <br />