<br />5. In Phase I of the amendment the pit walls will be <br />excavated vertically. Phases II-V will most likely be <br />excavated in strips. In both areas backfilling will occur <br />after mining is completed to achieve approximately a 3:1 <br />slope. <br />6. The present linear highwall is about 1040 feet. Once <br />Phase I of the present amendment is completed the linear <br />highwall footage will be reduced and in Phases II-V would <br />not exceed 900 feet. The current active pit is <br />approximately 1.7 acres. <br />7. The present manner of reclamation has been to backfill and <br />grade the mined out areas with salvaged overburden. <br />Sloping has been to approximately a 3:1 contour. Once the <br />mined areas have been re topsoil has been spread to <br />a depth of at least`~~ssix inches d the area reseeded. The <br />area has been regraded'ta tilend in with the adjacent <br />topography. <br />8. The permit boundary has been extended to include the <br />crusher and stockpile area southeast of Phase II. The <br />permit fee has also been included to cover this area. <br />9. Bluetop Paving occupied the area southeast of Phase II <br />which is designated as the crusher and stockpile area. <br />The area remains a relatively flat gravelled site with a <br />low berm along the south side. The site will require <br />little effort to put it into use in the future. <br />lO.Any asphalt plant location will be on compacted gravels <br />and be bermed as necessary to insure that a spill would <br />not leave the site. Any cleanup required would be <br />accomplished by using the dozers and loaders on site for <br />pickup and burial of the spilled material. <br />11.Within the area of major disturbance the following are <br />included: topsoil stockpiles, overburden (spoil) <br />stockpile, and the pit area. Within the area of moderate <br />disturbance the following are included: both areas shown <br />as crusher and stockpile locations, the access road to the <br />operation, and the area shown as mined and backfilled. The <br />area of minor disturbance includes that area which has <br />been backfilled, graded, topsoiled and seeded. Review of <br />