Phase IVc Summary No. 12 Page 2 043-2170 <br />• Ames continued production of bentonite-amended SLF at the screen plant and pug mill located above <br />the Ames materials yazd. Ames also continued production of Drain Cover Fill (DCF) material at the <br />screen plant by the secondary crusher. <br />Poly-Flex continued deployment of 80-mil single-sided textured LLDPE geomembrane in the Phase <br />Nc OSA. Geomembrane was installed in the Phase IVc OSA on the south facing slope of Raven Hill <br />downward to the Phase NbJNc tie-in. Poly-Flex deployed 80-mil single-sided textured LLDPE <br />geomembrane over an azea of approximately 128,317 square feet in the Phase Nc OSA during this <br />reporting period. Geomembrane panels C-434 through C-484 were deployed, seamed, and tested by <br />Poly-Flex. Destrucfive fusion and extrusion seam samples DFc-158 through DFc-173 and DXc-16 <br />through DXc-17 were mazked and removed. Destructive fusion and extrusion seam peel and shear <br />testing on samples DFc-152 through DFc-166 and DXc-16 were performed and passed per project <br />specification. <br />Ames continued hauling, placement and grading of DCF material into the Phase Nc OSA in the <br />western and central portion of the VLF, Raven Hill area. Ames placed DCF material and High Volume <br />Solution Collection (HVSC) piping per the project plans onto approved geomembrane panels. <br />r 1 <br />L_J <br />I • <br />A map of the azea worked during this reporting period is provided in Attachment C. <br />Field Monitorin¢ and Testing Activities <br />Golder observed construction activities associated with Phase Nc earthworks. All construction <br />materials and soil materials placed were verified as suitable, and construction methods were in <br />accordance with project specifications. <br />Golder observed excavation of the LDT outside the Phase IVc for trench dimensions and slope. <br />Golder observed placement, compaction, and moisture conditioning of SLF in the Phase Nc OSA for <br />subgrade prepazation, thickness, compaction, moisture-content, and materials used. The Golder CQA <br />earthworks monitor performed fifteen nucleaz moisture-density tests (SLNc-127 through SLNc-141). <br />Field test results aze presented in Attachment B. <br />Golder observed geomembrane deployment, documenting ambient temperature, panel dimensions, <br />thickness, seaming, tie-in overlap, and seam testing (trial seams, pressure testing). Geomembrane <br />installed in the Phase IVc OSA met the project specification. <br />Golder visually observed the placement of DCF in the Phase IVc OSA azea. Golder CQA monitors <br />(one monitor per dozer when dozers aze greater than 50 feet apart) observed DCF placement and <br />verified minimum thickness of 2 feet for finish grade, and 4 feet for haul traffic (i.e., Caterpillaz <br />Mode1740 articulated trucks). <br />Golder observed placement of HVSC piping in the Phase Nc OSA, verifying installation and layout <br />per the project plans. <br />en~rvo ~zrwy zs-Imyli zooa.doc GOIder ASSOCiateS lnC. <br />