My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2003-08-05_REVISION - M1980244
DRMS
>
Day Forward
>
Revision
>
Minerals
>
M1980244
>
2003-08-05_REVISION - M1980244
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/15/2021 5:49:54 PM
Creation date
11/21/2007 11:43:58 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
Revision
Doc Date
8/5/2003
Doc Name
Weekly Construction Report
From
CC & V
To
DMG
Type & Sequence
AM8
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
27
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Phase IVb Weekly Summary No. 26 Pase 2 <br />003-2203 <br />geomembrane deployment. Ames backfilled approximately 250 linear feet of anchor trench on the <br />2H:1 V riser slope, and south along the upper bench of the OSA slope. Ames also backfilled <br />approximately 100 lineaz feet of Phase IVb OSA anchor trench on the Phase III ore slope (9636 <br />elevation bench). <br />Ames hauled, placed, and compacted SLF material into the Phase IVb OSA, on the west and south <br />slopes of the Substation Hill. SLF material was worked, tested, and passed per project specification <br />prior to SLF surface acceptance. <br />Ames continued placement of high Volume Solution Collection System (HVSCS) secondary and <br />tertiary piping within the Phase IVb OSA limits, followed by DCF haul and placement per project <br />plans. Ames began a haul and placement of DCF onto the 2H: 1 V riser slope, south of the Low Volume <br />Solution Collection System (LVSCS) riser trench. Ames continued to haul and place DCF in the Phase <br />IVb OSA adjacent to the Phase IVa tie-in. Ames continued to haul and place DCF onto the Phase IVb / <br />Phase III ore slope, south west of the PSSA sump. <br />Ames continued production of DCF at the screen plant located neaz the Secondary Crusher. Ames also <br />continued limited production of SLF. <br />Poly-Flex continued deployment of 80-mil double-sided textured LLDPE geomembrane in the Phase <br />IVb OSA on the 2H:1 V LVSCS riser slope. Poly-Flex deployed 80-mil double-sided textured LLDPE <br />geomembrane over an azea of approximately 5,081 squaze feet in the Phase IVb OSA during this <br />reporting period. Geomembrane panels B-401, B-402, and B-409 were deployed, seamed, and tested by <br />Poly-Flex. No destructive fusion seam samples were marked on this section of liner. Destructive <br />extrusion seam sample DXb-25 was marked and removed. DXb-25 failed to meet project specification <br />and additional destructive samples (DXb-25a1, DXb-25a2, DXb-25b1, and DXb-25b2) were taken <br />across approximately 120 linear feet of extrusion weld until passing conditions were met. The <br />delineated failure across the seaming length was capped and extrusion welded and two additional <br />destructive samples were performed on the cap (DXb-26 and DXb-27). Destructive extrusion seam <br />peel and shear tests on 80-mil extrusion samples DXb-26 and DXb-27 passed project specification. <br />Poly-Flex resumed deployment of 80-mil single-sided textured LLDPE geomembrane in the Phase IVb <br />OSA on the west-facing slope of Substation Hill. Poly-Flex deployed 80-mil single-sided textured <br />LLDPE geomembrane over an area of approximately 283,990 square feet in the Phase IVb OSA during <br />this reporting period. Geomembrane panels B-403 through B-408, and B-410 through B-510 were <br />deployed, seamed, and tested by Poly-Flex. Destructive fusion and extrusion seam samples DFb-1li <br />through DFb-151 and DXb-28 were mazked and removed. Destructive fusion and extrusion seam peel <br />and shear tests on 80-mil single-sided textured geomembrane deployed during this reporting period <br />passed per project specification. <br />A map of the area worked during this reporting period is provided in Attachment C. <br />PhaseIVc <br />Ames performed no construction activities in the Phase Nc azea during this reporting period. <br />Phue IV6263uiy13-Iu1y19, 2003 Golder Associates Inc. <br />