My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2004-10-18_REVISION - M1980244 (24)
DRMS
>
Day Forward
>
Revision
>
Minerals
>
M1980244
>
2004-10-18_REVISION - M1980244 (24)
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/15/2021 5:49:54 PM
Creation date
11/21/2007 11:28:01 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
Revision
Doc Date
10/18/2004
Doc Name
Ph.IVc VOL.II Tech Specs
From
Golder Associates Inc.
To
DMG
Type & Sequence
AM8
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
96
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
® observe prepared subgrade prior to geosynthetic deployment; <br />®monitor and document geosynthetic material placement, trial seam testing, non- <br />destructive testing, seaming and repair operations, and destructive testing; <br />® identify seam samples for CQA destructive testing; <br />® assure that testing equipment used, and tests performed aze conducted according to <br />project SPECIFICATIONS and industry standards; <br />® perform or observe, document, and report test results to MANAGER as required; <br />® report any deficiencies to MANAGER that aze not corrected to the satisfaction of the <br />CQA Monitor, including design or project SPECIFICATION changes; and <br />® prepare a Construction Certification Report describing the construction, any deviations <br />from SPECIFICATIONS or, DRAWINGS and details, details of all field and laboratory <br />details, subgrade acceptance forms, test data, tests results (both laboratory and field), QC <br />submittals, geomembrane panel layout as-built prepazed by the CQA Monitor, <br />professional certification that construction was completed in compliance with the <br />DRAWINGS and SPECIFICATIONS. The report will be signed and sealed by the <br />CERTIFYING ENGINEER registered in the State of Colorado. <br />2.06 GEOSYNTHETICS MANUFACTURER: <br />The Geosynthetics Manufacturer, also referred to as the "MANUFACTURER", is responsible for <br />• production of the geosynthetic components outlined in this plan. Each MANUFACTURER must verify <br />prior to construction that the MANUFACTURER can produce material that meets the requirements <br />outlined in project SPECIFICATIONS. <br />2.07 GEOSYNTHETICS INSTALLATION CONTRACTOR: <br />The Geosynthetics Installation Contractor, also refereed to as the "CONTRACTOR" or <br />"INSTALLER", is responsible for installation of the geosynthetic components, as outlined in the <br />project SPECIFICATIONS. <br />The INSTALLER must meet the requirements outlined in the project SPECIFICATIONS. <br />The INSTALLER will be responsible for storage, handling, deploying, temporary geomembrane <br />anchoring, seaming, repairs and non-destructive testing, in accordance with the project plans, <br />SPECIFICATIONS and the INSTALLER'S internal quality control program. It is the INSTALLER'S <br />responsibility to see that all submittals aze received as outlined in the project SPECIFICATIONS. <br />2.08 EARTHWORKS CONTRACTOR: <br />The Earthworks Contractor, also refereed to as "CONTRACTOR" is responsible for proper delivery <br />and placement of earthwork components as outlined in the project SPECIFICATIONS. <br />PART 3.0 LINES OF COMMUNICATION <br />The CQA Monitor shall be capable of direct communication with the MANAGER, DESIGN <br />ENGINEER, CERTIFYING ENGINEER and CONTRACTOR at all times. Deficiencies that can <br />• <br />Section 01400.2 Page 3 of 11 Mazch 22, 2000 <br />Geosynthetic CQA Plan Golder Associates Revision 5 <br />I:W9IOBS\093-21)OWC CERTIFICATION REPORT\PHASE IVC OSA CERTWPPEND[CffSWPPENDIX E TECHMCAL SPECIFICATfONSW19W2R5 DOC <br />
The URL can be used to link to this page
Your browser does not support the video tag.