Phase IVb Weekly Summary No. 8 Page 2 003-2203 <br />Ames continued hauling and placement of Low Volume Solution Collection Fill (LVSCF) in Phase <br />IVb. <br />Ames utilized a Caterpillar 330 excavator with a baz attachment to taper the crest and shoulder area <br />of the in-place LVSCF material. <br />Ames performed excavation remediation activities for underground workings UG-485, UG~87, and <br />UG-488 and UG-315. Ames performed excavation and geogrid remediation ofUG-316. <br />Ames performed local cut to fills of SF materials along the south side of Substation Hill. A Cat D8 <br />dozer performed fill placement and a Cat 563 SDVR would compact the material per method <br />specification within the VLF limits. <br />Ames completed construction of the permanent diversion channel on the Substation Hill area. <br />Phase IVc <br />Ames performed confirmatory drilling activities associated with the Phase IVc construction area on <br />underground working UG-304, UG-508, and UG-291 during this reporting period. Ames performed <br />a blast at UG-304 on January 15"'. <br />Ames placed Cemented Rock frll (CR) at UG-288/289, and UG-498, and Structural Fill (SF) over <br />previously remediated workings at UG-288/289, UG-499, UG-500, UG-502, UG-503, and UG- <br />505/558. <br />Ames performed local cut to fills of SF materials along the access road on Raven IIil] and down slope <br />to temporary stockpiles above the Connolly haul road elevation. <br />Field Monitoring_and Testing Activities <br />Golder observed construction activities associated with Phase N earthworks. All construction <br />materials and soil materials placed were verified as suitable, and construction methods were in <br />accordance with project specifications. Removal of oversized and deleterious material from all fill <br />areas was observed. Golder observed Structural Fill (SF) placement in Phase IV for materials, lift <br />thickness, moisture content, and campactive effort. <br />Golder observed and documented excavation remediation activities associated with the Phase IV <br />underground working construction. Workings were designated as "Shallow or Deep" as defined in <br />the drawings and will be remediated accordingly. <br />Golder observed placement of SF, geogrid, and CR for underground working remediation. These <br />materials were placed in accordance with the drawings and specifications into excavated or open <br />underground workings. Golder obtained samples of LVSCF for laboratory index testing. Materials <br />supplied met specifications. <br />enau nro a,mms,s, zoosdoc Golder Associates Inc. <br />