Reclamation Costs <br />Task Description Time Needed Cost <br /># months <br />1 Move 15,000 cy of overburden from stockpile 1.0 $6000 <br /> to pit @ $0.40 per cy. <br />2 Rip 4.3 acres of bench azea @$250 per acre 0.1 $1075 <br />3 Move topsoil from stockpile with loader and 0.4 $6651 <br /> truck to benches and upper slopes of lake for <br /> the Phase 2 portion. This is 7" x 5.7 acres = <br /> 5364 cy. Use D-8 dozer for spreading = 5364 <br /> cy @ $1.24 per cy <br />4 Disc topsoil on 5.7 acres. Use farm tractor. 0.1 $1140 <br /> $200 per acre x 5.7 acres <br />5 Seed wetland fringe area (1.6 acres) @ $1000 0.1 $1,600 <br /> per acre. <br />6 Allow lake to fill and regrade settling pond 0.1 $300 <br /> and associated ditch. 500 cy Use D-8. 500 cy <br /> x $0.60 per cy <br />7 Reseed, mulch and fertilize all topsoiled azeas. 0.3 $5325 <br /> (7.1 acres) Drill seeding and crimp mulching <br /> will be employed on flat azeas and broadcast <br /> seeding will be done on the slopes greater than <br /> 3H:1 V. Cost is $750/acre x 7.1 acres <br /> <br /> Totals 2.1 $22,091 <br /> DMG Costs (21% x direct costs) $4,639 <br /> Total Bond Amount $26,730 <br />North R-34 Pit 1/07 <br />37 <br />