i r <br />• This road will be reclaimed within the permit boundary but will <br />be left for maintenance access to the U.S.B.R. Fountain Valley <br />Pipeline right-of-way for maintenance. An electric line will be <br />run into the mine site to provide power (440V) for the screen. <br />Dust from haul roads and screening will be controlled with water <br />spray methods and in accordance with our Fugitive Emissions <br />Control Plan from E1 Paso County. <br />The estimated timetable for each phase (5 acre area) is 4 years 9 <br />months. This timetable for each phase will overlap due to <br />reclamation occurring in one area and mining in an adjacent area. <br />It is anticipated that the entire permit area will be mined over <br />a 10 year to as long as a 15 year period. of course, this is <br />dependent upon the need for materials for Utilities projects. <br />• <br /> <br />