• Revision to Section 2.05.4(b) <br />Backfill Foundation Excavation <br />8,300 yd3 excavated - 2,000 yd3 hauled to backfill = <br />6,300 yd3 in site to be backfilled - no haul required. <br />6,300 yd3 =. 112.5 yd3/hr = 56 equipment hours <br />Cat 215, 56 hours @ $67.70 = $3,791 <br />Haul To Backfill Foundation Areas <br />996D loader with 4.5 yd3 bucket <br />Truck & Trailer @ 40 yd3 capacity <br />@ 15 mph trip = <br />To load <br />To dump <br />TOTAL CYCLE <br /> <br />.033 hours <br />.060 hours <br />.025 hours <br />.12 hours for one truck to load, <br />haul dump and return <br />2,000 yd3 to haul @ 40 yd3/trip = 50 trips <br />50 trips @ .12 hours/trip = 6 hours <br /> <br />751/70/25 Revised January 1985 <br />