Laserfiche WebLink
Revision to Section 2.05.4(b) <br />Trailer, 6 hours @ $12.36 = $ 74 <br />Tractor, 6 hours @ $51.75 = 311 <br />Loader, 6 hours @ $86.81 = 521 <br />TOTAL $906 <br />Backhoe to Fill Haul Material After Bumping <br />2,000 yd3 112.5 yd3/hr = 17.8 hours <br />Cat 215, 18 hours @ $67.70 = $1,219 <br />Summary of Facilities Removal <br />Building Removal $ 56,032 <br />Structure Excavation 5,010 <br />Concrete Removal 38,675 <br />Backfill Excavations 3,791 <br />Haul Additional Backfill 906 <br />• Backhoe to Complete Fill 1,219 <br />$105,633 <br />Rail and Tie Removal <br />16,737 LF @ $10/LF = $167,370 <br />Load, haul and dispose of RR ballast <br />24,000 yd3 <br />996D loader <br />Load time = .06 hours <br />Total circuit = .58 hours (to pit) <br /> <br />751/70/26 Revised January 1985 <br />