ase I a Weekly Summary No. 57 Page 2 <br />stwenty-four through twenty-nine. Ames continued excavation of the anchor trench along the eastern <br />limit of Phase IVa in preparation for geomembrane deployment. <br />• Ames continued construction of the three (3) 42" CSP's for the VLF access road by placing <br />reinforcing steel and concrete for the headwall and wingwall structures. Ames placed approximately <br />4 cubic yazds of concrete into the headwall on July IOa', approximately 12 cubic yards of concrete <br />into the wingwall footings on July 12a', and approximately 6 cubic yards into the wingwalls on July <br />13~'. <br />Ames continued and completed construction of the Phase IVa Leak Detection Trench (LDT) by <br />excavating the final section of trench and placing the sump. <br />~i <br />I <br />Poly-Flex continued deployment of 80-mil LLDPE geomembrane in the Phase IVa azea. Poly-Flex <br />deployed 80-mil single-sided textured LLDPE geomembrane over an azea of 102,227 squaze feet in <br />the Phase IVa azea during this reporting period. Geomembrane ganels P162 through P184 were <br />deployed, seamed, and tested by Poly-Flex. Destructive seam samples DF-66 through DF-76 were <br />marked, removed, and tested. <br />Phase IVb <br />Phase III diversion channel and at the western end of the PSSA floor. Prior to placement of SF, <br />Ames removed the existing 84-inch highway CSP. Ames also continued slope recontouring in the <br />Phase IVb azea on the northern PSSA slope. <br />Ames continued placement of Structural Fill (SF) in the Phase IVb azea. Ames placed SF in the <br />Ames hauled oversize material from the Phase IVb area to an uncontrolled fill site. <br />Ames continued removal of the old diversion channel. This work consisted of removal of the <br />concrete headwall and CSP's underneath the old Highway 67 alignment, removal of channel rip-rap, <br />and demolition and removal of a concrete drop-structure. <br />Ames continued removal of topsoil from the northwest face of the substation hill azea. Uncontrolled <br />fill material was placed by Ames adjacent to the Secondary Crusher fill. <br />Ames continued removal of Drain Cover Fill (DCF) from the Phase III liner neaz Chicken Hawk Hill <br />and at the new LOB. <br />Ames performed confirmatory drilling activities associated with the Phase IVb construction area on <br />underground workings UG-493, the Ophir tunnel, UNK-11, and UNK-13 . <br />Ames performed excavation remediation activities for underground workings UG-252, UG-493, UG- <br />547, UNK-13, and UNK-14. These workings were observed and verified to be "Shallow or Deep" as <br />defined in the drawings and will be temediated accordingly. <br />Ames resumed construction of the Phase Nb Primary and Secondary underdrains by excavating the <br />trenches and placing materials. <br />Phase lVeSNune30.1uly U.doc Golder Associates Inc. <br />