<br />' feature in the solution pipelines. <br />' Response: BMR does not intend to install no-drain back-pressure valves in <br />the solution pipelines due to the harsh winter temperatures <br />typically experienced at the site. BMR is concerned that pipes <br />1 with standing water will freeze and then rupture. BMR has sized <br />the lined pipeline ditch to accommodate anticipated flows in the <br />event of a large pipeline leak, The lined ditch will direct these <br />flows either to the barren pond or to a lined catchment area <br />located at the mill site. Designs for the mill site lined <br />catchment area are included in revised Section D.5. <br />Exhibit D, Section D.5 revised 2J15J89. MLRD considered BMG response <br />adequate. <br />1 c. It is unclear whether the barren solution pipeline will run from <br />the mill to the barren pond or if the pipeline will run from the <br />mill directly to the top of the heap. Please clarify. <br />Response: The pipeline will run to the barren pond. <br />No application change necessary. <br />I 32. The pad solution collection trench shown on Exhibit C-8 does not appear <br />to be the same as the series of collection trenches constructed through <br />Stages 1-6 as illustrated in this section. Please clarify. <br />Response: As discussed under Comment 27, the appropriate figures have been <br />revised and should now proviae the necessary clarification. The <br />~~ reader should note that the staged construction berms should not <br />be confused with the center collection drain. <br />Figures C-11, C-12, D.7.4.1-1, D.7.4.1-2, D.7.4.1-3 and D.7.4.1-4 revised <br />2/15J89. <br />33. It will be necessary to provide a statement certifying that each <br />1 particular phase cf the leach pad (including primary and secondary <br />liners} was constructed to the specifications approved 6y the Board. <br />This statement must 6e submitted at the completion of each construction <br />' stage. In particular, test results on )finer seaming and collection <br />channel connections between stages should be presented after <br />completion. Please commit to these submittals. <br />Response: Construction of each phase of the leach pad will be supervised <br />by a registered professional engineer. Certification that each <br />phase of the leach pad construction was constructed to the <br />specification approved in the permit will be submitted following <br />construction completion. <br />Exhibit D, Section D.7.1 revised 4/20J89. <br />' 34. Figure C-9 and Figure C-]0, Detail 11, specify that a facility pipeline <br />corridor exists along the south and east heap perimeter, but dines not <br />identify the extent of the corridor. Please address whether it extends <br />i <br />