Newmont‐Cripple Creek & Victor Gold Mine  <br />Technical Specification No. 01400‐2 GEOSYNTHETICS CQA  <br />VLF2 Phase 3  <br />Project No.475.0106.049  <br />August 27, 2021  <br />  <br />  <br />  <br />Technical Specification No. 01400‐2 Geosynthetics CQA    Page 2  <br />The MANAGER is also responsible for coordinating construction and CQA activities for the  <br />project.  <br />The MANAGER shall serve as communications coordinator for the project initiating  <br />preconstruction and resolution meetings. As communications coordinator, the MANAGER shall  <br />serve as a liaison between all parties involved in the project to ensure that ongoing  <br />communications are maintained. The MANAGER and CERTIFYING ENGINEER shall also be  <br />responsible for the resolution of all CQA issues that arise during the installation of the  <br />geosynthetics.  <br />Duties for this position include the following:  <br /> review and approval of design DRAWINGS and project SPECIFICATIONS for all  <br />geosynthetic components of the valley leach facility;    <br /> preconstruction coordination with the CQA MONITOR to ensure that the CQA  <br />MONITOR has performed similar reviews of the design DRAWINGS and project  <br />SPECIFICATIONS to ensure that the CQA Plan can be implemented;  <br /> coordination of all construction activities associated with the various CONTRACTOR(S);  <br /> scheduling and coordinating construction activities with required CQA testing and activities;  <br /> overseeing the construction quality control operations performed by the CONTRACTOR(S);  <br /> approve specific corrective measures to be implemented during construction when  <br />deviations from the SPECIFICATIONS occur;  <br /> ensure that required quality control testing has been performed in accordance with the  <br />CQA Plan and to the satisfaction of the CQA MONITOR; and  <br /> ensure that the CQA personnel are provided with all documentation required in the CQA  <br />Plan and project SPECIFICATIONS.  <br />2.3. Design Engineer  <br />In this CQA Plan the DESIGN ENGINEER and Engineer of Record (EOR) refers specifically to  <br />NewFields who has assumed the role of DESIGN ENGINEER after a thorough review of design  <br />documents to include, but not limited to, the DRAWINGS and SPECIFICATIONS. The DESIGN  <br />ENGINEER or the CERTIFYING ENGINEER identified in section 2.4 below, is responsible for  <br />approving all DRAWING and SPECIFICATION changes, modifications, or clarifications  <br />encountered during construction.  <br />2.4. Certifying Engineer  <br />In this plan, CERTIFYING ENGINEER refers specifically to NewFields. CERTIFYING ENGINEER is  <br />the individual or firm responsible for certifying the construction was performed in compliance