Cost Summary Worksheet Cont'd Task#000 Page 2 of 4
<br /> 063 Rip BC Walk Road RIPPER 4 2.24 $3,553
<br /> 064 Rip D-main Pit Haul Roads RIPPER 4 8.40 $13,311
<br /> 065 Rip West Ash Haulroads(West Ash,West Ashl RIPPER 4 5.98 $9,474
<br /> and West Ash 2)
<br /> 066 Rip LOM Haul Roads(F2 and F2-G5) RIPPER 4 8.76 $13,879
<br /> 067 Rip A Pit Haul Roads(Middle A and North A) RIPPER 4 6.43 $10,184
<br /> 068 Rip N Pit Haul Roads RIPPER 4 5.38 $8,526
<br /> 072 Rip East A Haul Roads(East A and East A Split) RIPPER 4 2.96 $4,690
<br /> 074 Rip Access Road(Tasks 042-059) RIPPER 4 3.11 $4,926
<br /> 075 Rip K Pit Haul Roads(KMain,Kl,K2 ,K3) RIPPER 4 2.12 $3,363
<br /> 076 Rip K Pit Haul Roads(TR106) RIPPER 4 3.37 $5,338
<br /> 077 Rip I/J Roads(I/J Spoil,I Mid,I West) RIPPER 4 4.55 $7,214
<br /> 078 Regrade Coyote Impoundment DOZER 2 288.69 $208,963
<br /> 079 Regrade Middle Pyeatt Impoundments DOZER 1 51.73 $18,721
<br /> Impoundment(1,2,3)
<br /> 080 Regrade Far East Buzzard Impoundment DOZER 1 0.56 $204
<br /> 081 Regrade Sage Impoundments(1 and 2) DOZER 1 18.91 $6,845
<br /> 082 Regrade West Horse Impoundment DOZER 1 3.52 $1,273
<br /> 083 Regrade Impoundment H DOZER 1 7.29 $2,637
<br /> 084 Regrade Industrial Waste Pond DOZER 1 7.47 $2,703
<br /> 085 Regrade Deal 1 and 2 DOZER 1 9.83 $3,835
<br /> 086 Regrade Deacon 1,2 and Jeffway 1,2 DOZER 1 94.72 $36,962
<br /> impoundments
<br /> 087 Regrade W.Buzzard#4 Impoundment DOZER 1 6.00 $2,343
<br /> 088 Regrade E.Buzzard#3 Impoundment DOZER 1 7.04 $2,747
<br /> 089 Regrade Diversions DOZER 1 61.42 $17,231
<br /> 090 Replace Topsoil on Ash Pits(ASH I) SCRAPERI 1 6.32 $36,876
<br /> 090A Replace Topsoil on Ash Pits(ASH2) SCRAPERI 1 15.52 $90,571
<br /> 090B Replace Topsoil on Ash Pits(A92-4 to Pit) TRUCKI 1 107.16 $260,456
<br /> 091 Replace Topsoil on D/E Pits(Truck/Excavator) TRUCKI 1 416.57 $877,558
<br /> 091A Replace Topsoil on D/E Pits(D97-1) SCRAPERI 1 25.97 $119,668
<br /> 091B Replace Topsoil on D/E Pits(D1-07) SCRAPERI 1 3.46 $15,940
<br /> 092 Replace Topsoil at C Pit SCRAPERI 1 110.60 $645,337
<br /> 096 Replace Topsoil at West Panel,BC rd,Shop SCRAPERI 1 16.07 $93,745
<br /> (Scraper)
<br /> 096A Replace Topsoil at West Panel,BC rd,Shop TRUCKI 1 147.14 $309,961
<br /> (Truck/Excavator)
<br /> 097 Replace Topsoil at East Panel Ponds,A road SCRAPERI 1 170.98 $997,685
<br /> 098 Re-topsoil Johnson Coal Stockpile SCRAPERI 1 5.03 $29,359
<br /> 099 Replace Topsoil at Dragline Walk Road(ASH4) TRUCKI 1 8.17 $14,567
<br /> 099A Replace Topsoil at Dra line Walk Road(ASH I) TRUCKI 1 33.14 $59,089
<br /> 100 Facilities Area REVEGE 1 75.00 $36,711
<br /> 100A Seed D Pit Range A-B REVEGE 1 319.30 $351,590
<br /> 101 Roads(including BC road)below 6700' REVEGE 1 196.00 $96,085
<br /> 102 Finish Grading I/J Pit GRADER 2 21.73 $13,139
<br /> 103 Ponds below 6700'(Coyote,Sage,E Buzzard) REVEGE 1 26.00 $12,727
<br /> 104 Johnson Coal Stockpile REVEGE 1 12.00 $6,167
<br /> 105 topsoil piles below 6700' REVEGE 1 27.00 $13,265
<br /> 107 Roads:>6700 ft.-Rangeland with Shrubs REVEGE 1 54.00 $43,633
<br /> 108 Ash pit.-Rangeland with Shrubs REVEGE 1 115.00 $93,061
<br /> 109 Seed D/E Pit Range B REVEGE 1 15.00 $10,331
<br /> 111 Ponds above 6700'(Deal,Deacon,Jeffways,West REVEGE 1 19.00 $15,062
<br /> Horse)
<br /> 112 topsoil piles above 6700' REVEGE 1 5.00 $4,106
<br /> CIRCES Cost Estimating Software