Walstrum Spur Amendment, Exhibit E— Reclamation Plan April 2021 <br />6.0 RECLAMATION SCHEDULE <br />6.4.5(2)(e) A plan or schedule indicating how and when reclamation will be implemented. Such plan or schedule <br />shall not be tied to any specific date but shall be tied to implementation or completion of different stages of the <br />mining operation as described in Rule 6.4.4(e). The plan or schedule sha// include: <br />6.4.5(2)(e)(i) An estimate of the periods of time which will be required for the various stages or phases of <br />reclamation; <br />6.4.5(2)(e)(ii) A description of the size and location of each area to be reclaimed during each phase; and <br />6.4.5(2)(e)(iii) An outline of the sequence in which each stage or phase of reclamation will be carried out. <br />Reclamation within the Existing Quarry will occur as previously approved. Parcel 62, added as part of the Spur <br />Amendment, will be reclaimed in conjunction with the reclamation of the adjacent Existing Quarry West Slope <br />Section. The eastern one-third of Parcel A1, added as part of the Spur Amendment, will be reclaimed as <br />Industrial/Commercial/Public Gathering in conjunction with the reclamation of the adjacent Existing Quarry North <br />Slope Section (see Exhibit F-1). <br />Reclamation on benched areas in the Spur Amendment will occur concurrently with the mining operation. Once <br />each bench is mined to its finished elevation, the Operator will begin mining the next lower level while simultaneously <br />reclaiming the previously finished bench. <br />7.0 RECLAMATION DETAILS <br />6.4.5(2)(f) A description of each of the following: <br />6.4.5(2)(f)(i) Final grading - specify maximum anticipated slope gradient or expected ranges thereof,� <br />6.4.5(2)(f)(ii) Seeding - specify types, mixtures, quantities, and expected time(s) of seeding and planting; <br />6.4.5(2)(f)(iii) Fertilization - if applicable, specify types, mixtures, quantities and fime of application; <br />6.4.5(2)(f)(iv) Revegetation - specify types of trees, shrubs, etc., quantities, size and location; and <br />6.4.5(2)(f)(v) Topsoiling - specify anticipated minimum depth or range of depths for those areas where topsoil will <br />be replaced <br />7.1 Final Grading <br />Grading will be performed to create a final topography appropriate to the planned post-mining land use and mimic <br />surrounding natural slopes and cliffs. All grading will be done in a manner to control erosion and to protect areas <br />outside the affected lands from slides or other damage. All backfilling and grading will be completed as soon as <br />feasible after the mining process has been completed. <br />Reclaimed Quarry Floor <br />The final quarry floor will be sloped down at approximately 0.5% to 0.6% from east to west to establish positive <br />drainage to the main entrance at an approximate elevation of 7,220 feet. Stormwater Best Management Practices <br />(BMP's) will be installed near the main entrance for treatment prior to discharge under the existing stormwater <br />discharge permit. Finished grades are presented in Exhibit F(F-1 and F-2). The toe of the completed slopes within <br />the Existing Quarry will be at an approximate elevation of 7,240 feet. The quarry floor will be graded for future use <br />and stabilized against erosion to maintain the surface and drainage. The toe of mined slopes will progressively <br />increase towards the eastern end of the Spur Amendment to a maximum toe elevation of 7,270 feet. Typical sections <br />for reclaimed slopes are illustrated in Exhibit F(F-1 and F-2). <br />Slope Reclamation within Spur Amendment <br />The reclaimed slopes within the Spur Amendment will have an overall maximum slope of 1 H:1V above an elevation <br />of 8,000 feet and 0.6H:1V below 8,000 feet. After mining is completed, the mined slopes that have not been <br />� TETRA TECH P a g e 6 � 7 <br />