Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/23/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, 65 degrees <br /> From: 9:45 To: 10:45 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 1 1 Kessler Reclamation 5 10 <br /> AGW 1 5 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 1 Excavator 1 10 <br /> Loader 1 10 <br /> Water Truck 1 10 <br /> Haul Truck 1 10 <br /> Skid Loader 1 10 <br /> Compactor Roller 1 10 <br /> Description of Work Performed: <br /> Material screening continued. <br /> Technician found parts to order for Kessler's compactor, but there will be a two week delay. <br /> A larger roller was delivered to the site yesterday afternoon. <br /> The first lift was applied and packed in the ditch. The tester from AGW was on-site to test compaction. <br /> The first lift passes all compaction tests. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> The second lift is planned for tomorrow, with the AGW tester on-site again. <br /> A gravel delivery is planned for Saturday. <br /> Kessler Reclamation will be back on-site Sunday as well to continue screening for the third lift. <br /> Inspector: Evan Valencia Date: 9/23/2020 <br />