Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/22/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, 65 degrees <br /> From: 9:45 To: 10:45 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam Lowe) 1 1 Kessler Reclamation 5 10 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Excavator 1 <br /> Loader 1 <br /> Water Truck 1 <br /> Haul Truck 1 <br /> Skid Loader 1 <br /> Compactor Roller 1 <br /> . ................................. . <br /> Description of Work Performed: <br /> Material screening continued. <br /> Technician working on trying to fix the roller compactor. <br /> A larger roller is being delivered to the site this afternoon. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Kessler is trying to keep busy on the NWRP while the roller is out of commission. <br /> Calvin is ordering PVC for the drain behind the seal wall. <br /> We measured for gravel volume today; 8 CY or 12 tons. <br /> Inspector: Sam Lowe Date: 9/22/2020 <br />