Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/24/2020 <br /> Contractor: Ensero Solutions <br /> Shift <br /> Hours Worked Weather: Clear sky, 65 degrees <br /> From: 12:00 To: 15:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No. Hours <br /> Oversight (Evan Valencia) 1 4 Kessler Reclamation 5 11 <br /> AGW 1 6 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Excavator 1 11 <br /> Loader 1 11 <br /> Water Truck 1 11 <br /> Haul Truck 1 11 <br /> Skid Loader 1 11 <br /> Compactor Roller 1 11 <br /> Description of Work Performed: <br /> Material screening continued. <br /> The second lift was applied and compacted along alignment.The tester from AGW found all test sites to p <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Evan Valencia Date: 9/24/2020 <br />