Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 11/16/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, windy, 55 degrees <br /> From: 11:00 To: 12:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Jon Webb) 1 1.5 Kessler Reclamation 5 8 <br /> Contractor Equipment No. TotHouaI Subcontractor Equipment No. HouTotrs <br /> Passenger truck 1 1 Excavator 1 j 4 <br /> Grizzly 1 4 <br /> Loader 1 4 <br /> Haul Truck 1 4 <br /> Description of Work Performed: <br /> Work on the road crossing continued. Screened material was used to backfill trenches on the sides of the <br /> road. Berm work started in the afternoon. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Jon Webb Date: 11/16/2020 <br />