Laserfiche WebLink
Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/19/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, no wind, 80 degrees <br /> From: 13:00 To: 14:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 1 1.S Kessler Reclamation 8 10 <br /> Contractor Equipment No. TotHours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 1 Pump trailer 1 10 <br /> Description of Work Performed: <br /> First truck at 10:OOam. <br /> 32 CY of concrete poured. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> Concrete pump was having clogging issues.These were alleviated with Lime to clean the hoses, so <br /> there was no ill effect to productivity. <br /> Inspector: Evan Valencia Date: 10/19/2020 <br />