Laserfiche WebLink
Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/20/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, no wind, 80 degrees <br /> From: 8:00 To: 14:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam Lowe) 1 6.5 lKessler Reclamation 8 10 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 1 Pump trailer 1 10 <br /> Description of Work Performed: <br /> First truck at 8:OOam. <br /> 24 CY of concrete poured; 25 CY ordered <br /> Finished filling the geoweb today. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Sam Lowe Date: 10/20/2020 <br />