Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/16/2020 <br /> Contractor: Ensero Solutions <br /> Shift <br /> Hours Worked Weather: Clear sky, no wind, 80 degrees <br /> From: 10:30 To: 14:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam Lowe) 1 4 Kessler Reclamation 7 10 <br /> Billy Ray 1 2 <br /> Tim Cazier (DRMS) 1 2 <br /> Amy Eschberger 1 2 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Pump trailer 1 10 <br /> Description of Work Performed: <br /> First truck at 6:OOam. Two more trucks at 10:30am and 12:20pm <br /> 24 CY of concrete poured <br /> State pointed out the slope below the haul road looks more than a 2:1. Will get survey next week. <br /> Inspection by the DRMS to see channel liners and concrete placement. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Sam Lowe Date: 10/16/2020 <br />